|
The Construction Lien Law - How Will
It Impact Your Business?
By Peter J. Smith Construction
Litigation Partner
In the last three weeks of the Florio administration,
the Construction Lien Law was signed. The law repealed
the century old Mechanic's Lien Law and
eliminated the pre-filing requirements of a Mechanic's
Notice of Intention, the filing of general contract
documents, and the filing of a Stop Notice. The law
took effect on April 22, 1994. Projects for which
a construction permit had been issued prior to
April 22, 1994 will continue to be governed by the
Mechanic's Lien Law.
The predominant features of the Construction Lien
Law include (1) the ability to file a lien within
90 days after last furnishing labor, materials, or
services to a project without the necessity for
any preliminary filing and (2) the prohibition of
provisions requiring a waiver of lien rights.
Special procedures are adopted within the
Construction Lien Law governing liens
on residential projects.
Because lien waivers were expressly allowed
under the Mechanic's Lien Law, actual
lien filings have been a rare exception
on construction projects in the State. That
will no longer be the case. All parties
in the construction process -- owners,
design professionals, lenders, general
contractors, subcontractors, and suppliers
-- have new rights and responsibilities under
the Construction Lien Law that effect
a dramatic change in the status quo.
The following are selected highlights of the
new Construction Lien Law.
- Equipment used on-site for the improvement
of real property, including rental equipment,
can be the subject of a lien.
- Improvements are defined as any actual
or proposed physical change to real property
by the provision of work or services,
whether or not any physical change is
undertaken. Plans prepared by a licensed
engineer will generally constitute an
improvement and, regardless of whether
they are actually used, can be the subject
of a lien.
- The responsibility of the owner for
one or more lien claims shall not be greater
than the total amount of the contract price
between the owner and the contractor, less
the amount of payments made, if any, prior
to the receipt of a copy of the lien by the owner.
- A lien claim filed by a subcontractor or
supplier is limited to the amount of the
subcontract or purchase order price, less
payments prior to receipt of a copy of the
lien, or the amount set forth above, whichever is less.
- All rights to enforce a lien are forfeited if
suit is not commenced in the Superior Court within
one year of the date of the last provision
of work, services, materials or equipment or
within 30 days following receipt of written notice
from the owner requiring claimant to commence an
action to establish the lien claim.
- Liens that are willfully overstated or are
without basis expose the claimant to attorneys
fees and the inability to assert future lien
claims on the project for the work in question.
Likewise, a frivolous defense to a lien claim
may result in responsibility for attorneys fees.
- The Construction Lien Law dictates and sets
forth a form of Notice of Unpaid Balance and
Right to File Lien ("NUB"). This is a mandatory
pre-lien filing on a residential construction contract;
it is optional on other construction contracts. Its
purpose is to advise the owner that a potential
construction lien may be filed within the 90 day
period following the date of the provision of the
last work, services, materials or equipment. The
filing of a NUB is not a lien claim, nor does it
extend the time for the filing of a lien claim.
A lien claim relates back to the filing of a
NUB in establishing priority of the lien claim over
other filings, including mortgages.
- The lien claim may be discharged (1) upon
the filing with the County Clerk of a bond in
the amount of 110% of the lien claim, (2) upon
receipt of a certificate discharging the lien
claim signed by the lien claimant, or (3) pursuant
to an Order of discharge by the court.
- If required in the contract or upon written
request from an owner to a contractor or subcontractor,
the contractor or subcontractor shall, within 10 days,
provide the owner with an accurate and full list of
the names and addresses of each subcontractor and
supplier who may have a right to file a lien.
- Waivers of construction lien rights are declared
to be against public policy, unlawful, and void, unless
given in consideration for payment of the work, services,
materials or equipment provided or to be provided, and
such waiver shall be effective only upon and to the
extent that such payment is actually received.
Lien filings should increase dramatically under the Construction
Lien Law. Professionals, contractors and their suppliers
will have new hope for payment on problem jobs. Owners
and lenders will have new concerns in clearing title on
projects as a result.
For further information, contact Peter J. Smith at (973) 535-0500.
©1995 Connell Foley LLP . The foregoing is provided for informational purposes only and not as legal advice. Any questions about the law or your rights and obligations should be reviewed by legal counsel who is engaged by you and is provided with your specific fact situation.
|